EVENT START DATE: November 13, 2017
EVENT START TIME: 5:07 PM
LOCATION: GravityServers IGW Tukwila Datacenter
NEW RESOLUTION ETA: 11/15/2017 – 10.30AM
IMPACT OF POWER EVENT: NO INTERRUPTION

We have received confirmation from SCL that they have completed the Pole install and power restoration work. Due to the size of the electrical load, SCL has to gradually restore power to the neighborhood in order to prevent system overload. As of 9.00AM this morning, they have provided an estimate of 2 hours for gradual restoration. We should have power back online shortly here.

In anticipation of the power restoration, our team is on full standby. We will evaluate the quality of electrical power and will eventually perform power transfer back from Generator to utility.



Wednesday, November 15, 2017







« Back